Semester 1
Milestone | Completion | Start Date | End Date |
Website | 100% | 9/12 | 9/15 |
Initial Budget | 100% | 9/12 | 9/17 |
Project Plan | 100% | 9/12 | 9/17 |
FMEA Table | 100% | 10/5 | 10/6 |
Major Parts Purchasing | 100% | 10/18 | 12/8 |
Mid Report | 100% | 10/20 | 10/24 |
Final Report | 100% | 12/1 | 12/11 |
Final Presentation | 100% | 12/1 | 12/8 |
Semester 2
Milestone | Completion | Start Date | End Date |
Semester Plan | 100% | 1/18 | 1/24 |
Basic Object Detection | 100% | 1/24 | 2/2 |
Ethics Document | 100% | 2/21 | 2/25 |
Portable Touchscreen Monitor | 100% | 2/7 | 3/2 |
Major Parts Purchasing | 100% | 1/30 | 4/4 |
Presentation Poster | 100% | 4/11 | 4/18 |
Assembly of Robot | 80% | 3/9 | - |
Final Report | 25% | 4/4 | - |